The neutral-point voltage to an earth-fault IED is checked. The voltage is normally
0.1 to 1V secondary. However, voltage can be considerably higher due to
harmonics. Normally a CVT secondary can have around 2.5 - 3% third-harmonic
voltage.
15.3.2.8
Restoring
Maintenance is very important to improve the availability of the protection system
by detecting failures before the protection is required to operate. There is however
little point in testing healthy equipment and then putting it back into service with
an open terminal, with a removed fuse or open miniature circuit breaker with an
open connection, wrong setting, and so on.
Thus a list should be prepared of all items disturbed during test so that all can be
put back into service quickly and without overlooking something. It should be put
back into service item by item and signed by the responsible engineer.
Section 15
1MRK 504 088-UEN C
Commissioning and maintenance of the fault clearing system
218
Installation and commissioning manual
Summary of Contents for RELION RET670
Page 1: ...Relion 670 series Transformer protection RET670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 82: ...76...
Page 88: ...82...
Page 94: ...88...
Page 104: ...98...
Page 110: ...104...
Page 210: ...204...
Page 230: ...224...
Page 239: ...233...