<2. Analyzer Preparation>
2-2
IM 12Y18A03-01EN
1st Edition : Oct. 04, 2019-00
711
(28)
628.7
(24.75)
472 (18.6)
218 (8.6)
Mounting holes 4-ø12.7 (0.5)
Unit: mm (inch)
177.8 (7.0)
44 (1.75)
17
(0.68)
Figure 2.1 Mounting Dimensions
NOTE
• Select a site for the analyzer that allows it to be permanently bolted with ample height for
atmospheric drain operation. Be sure that there is ready access to the electronic controls,
calibration port and electrodes.
• A clearance of 15 inch (about 40 cm) must be allowed above the flow cell calibration port.
Insert the pipet vertically (not angled) during the calibration.
• The analyzer location must permit connections to a sample line, drain and AC power supply
and any connections for output devices.
• The analyzer should be mounted as close to the sampling point as possible. This ensures
the fastest possible response to a changing sample condition. Refer to the Appendix,
Sample Conditions section.
• For proper flow cell operation, the analyzer must be installed straight and level upon its
mounting location. Failure to level the analyzer may cause poor siphoning in the flow cell.
n
Instructions
1. Prepare the mounting holes. Carefully lift the analyzer and bolt it into place. Do not lift the
analyzer by holding on to any of the plumbing or fluid handling components.
2. Connect a waste line to the outlet of the analyzer, which is 3⁄4’’ NPT male. The waste
line should be connected to a drain of sufficient capacity, 0.5 inch (1.27 cm) OD is
recommended.
3. Connect a sample line to the inlet of the analyzer, which is 1⁄4’’ NPT female. It is
recommended that a shutoff valve be installed at the sampling point.