Set up the lift on firm and level ground only.
Ensure that all caster safety brakes on the chassis are engaged during set up.
Transport position of
lateral outriggers:
Lowering
outriggers:
Aligning
outriggers:
a)
b)
c)
90°
The models GML 800+ /20 and /25 reach
lifting heights of more than 5 meters. In order
to increase the stability of the lift, the lateral
outriggers must always be installed.
The models GML 800+ /10 and /15 reach a
maximum lifting height of 5 meters. The
installation of lateral outriggers for the models
/10 and /15 is therefore optional.
(Model type see nameplate)
1.
Hold the outrigger firmly. Press down the
brake plate (a) on the support strut (b). Lower
the outrigger towards the front until the
caster is approximately 5 - 10 cm from the
work surface.
Setting Example
90° lateral outrigger alignment.
2.
Pull the locking pin (c) on the adjustment
plate upwards and maintain a solid grip on it
in order to rotate the outrigger to the desired
position.
Fig. 2.1
3.
To secure the outrigger, release the locking
pin (Fig. 2.1). Ensure that the locking pin
slips correctly into the adjustment notch (Fig.
2.2). Shake the outrigger lightly to verify that
the locking pin is correctly locked in place.
4.
Repeat steps 1 - 3 for the second outrigger.
1.
NEVER operate the GML/K unless the weight box is completely filled!
2.
Never operate models GML 800+ /20 and /25 (Lifting height > 5,00m) without lateral outriggers!
3.
Both lateral outriggers must have the same alignment on each side.
4.
The locking pins must be correctly locked in the notch on the adjustment plate.
5.
Never move the lift with a raised load! Only allow for minor position changes.
6.
Avoid sudden movements.
Installation Lateral outrigger
at /20 + /25 models.
Lateral outriggers are as standard on all /20 an /25 models.