Glass and Material Lift
GML 800+
40
Operating Manual
GML 800+
Operate
the lift on firm and level ground only. Perform a PRE-OPERATION function test and convert the lift to
the operating position as described in the section headed “Installation “.
Ensure that all safety brakes on the swivel casters are engaged when working with a load.
The 230/110V Electric Winch
1.
Center the load on the loading accessory
and secure it against toppling.
2.
Use the cable extension in order to connect
the plug of the control system to a 230/110 V
socket.
WARNING!
Use the cable drum, unwind the cable
completely from the drum in order to
avoid the possibility of a short circuit
caused by overheating!
Control System:
a)
Right side
b) Left side
3.
To
switch on
the winch, insert the key into
the key switch 8) and turn it TO THE LEFT. When
the green signal lamp 4) is on, the winch is
ready to be operated.
4.
Raise
the load by turning the rotary switch
on the cable control 1) to the upwards switch
setting FOR RAISING 2). As soon as the rotary
switch is released the winch will automatically
stop.
5.
Lower
the load by turning the rotary switch
on the cable control 1) to the downwards
switch setting FOR LOWERING 2). As soon as
the rotary switch is released the winch will
automatically stop.
6.
To
switch off
the winch return the key in
the key switch back to a vertical position. The
green signal lamp will go off if the current is
turned off.
c)
Underneath
IMPORTANT!
The lift has two automatic limit switches that
deactivate the rotary switch of the control
system and automatically stops the winch
immediately, when the loading accessory
has either reached its lowest position
(when LOWERING) or its highest position
(when RAISING).
Emergency release:
If the lift is malfunctioning, it is crucial that
the electric emergency release is deployed.
It automatically lowers the loading accessory
and activates the red signal lamp 5). If there
is a malfunction the winch and cable control
system will not operate due to safety
requirements. Call a service technician!
c) Cable Control
1
2
3
4
Emergency
Stop
10)
Supply line to automatic limit switch
11)
Emergency release
12)
Supply line to winch
6
1)
230/110V Supply line
2)
Fuse
3)
Operating hours counter
reader
4)
Signal lamp GREEN
(operational readiness)
5)
Signal lamp RED
(malfunction)
6)
24 V Accessory port
(electric. crane outrigger)
7)
Emergency stop switch
8)
Key switch
(On/Off)
9)
Supply line to the Cable control
1)
Rotary switch Raising/Lowering
2)
Switch setting RAISING
3)
Switch setting LOWERING
4)
Accessory Button
(electric. Crane outrigger)
5)
Emergency stop switch
6)
Supply line to winch control system
Raising and Lowering with an AC-Electric Winch.
Operating the electric winch on AC-Models (230/110V).
Stop
10
11
12
5