Installation and operating instruction
Gas condensing unit WTC-GB 15-B Compact and WTC-GB 25-B Compact
7 Commissioning
83309302 1/2018-05 La
116-196
23. Optimise O
2
content at min. load
A correction is not necessary, if the O
2
content is within the permissible range.
Min load
O
2
content
Natural Gas
4.0 … 6.0 %
Liquid Petroleum Gas
4.3 … 6.3 %
Repeat procedure for min load.
Carry out flue gas measurement, enter values in the test sheet of the engineers
report.
Select
and confirm.
The commissioning wizard is closed.
Commissioning
Commissioning concluded successfully
24. Concluding work
DANGER
Risk of explosion due to leaking gas
Improper service work can lead to escaping gas and explosion.
After working on the gas combi valve, close the screw at the measuring point
and check for leaks.
If necessary, configure inputs and outputs according to the application
[ch. 6.6.9.5].
Close the test points and close covers.
Enter combustion values and settings in the commissioning record.
Inform the operator about the use of the equipment.
Insert the operating instructions enclosed into the inside of the control unit flap.
Hand the installation and operating manual to the operator and inform him that
this must be kept on site.
Point out to operator that the installation should be serviced annually.
Write the type of gas set onto the name plate.