4. The burner must be set according to the appliance application and
commissioned checking that all combustion parameters are as recommended in
the appliance technical manual.
5. Warmflow recommends that the in line and burner oil pump filters are inspected
and if required replaced frequently during burner use, before the burner start up
following a long period of discontinued operation and even more frequently where
contamination has occurred. Particular attention is needed when inspecting and
checking for fuel leakages from seals, gaskets and hoses.
INSTALLER/SERVICER NOTES
1. During the burner installation, check that the gasoil and bio fuel blends are in
accordance with Riello recommendations (please refer to the chapters “Technical
Data” and “Guidance for the use of bio fuel blends within the burner technical
manual).
2. If a Bio blend is in use the installer must seek information from the end user that
their fuel supplier can evidence that the blends of fuel conform to the relevant EN
standards.
3. Check that the materials used within the oil tank and ancillary equipment are
suitable for bio fuels. If in doubt contact the relevant supplier or manufacturer.
4. Particular attention should be given to the oil storage tank and supply to the
burner. Warmflow recommends that existing oil storage tanks are cleaned and
inspected and any traces of water are removed BEFORE bio fuel is introduced
(Contact the tank manufacturer or oil supplier for further advice). If these
recommendations are not respected this will increase the risk of contamination
and possible equipment failure.
5. Warmflow recommends a good quality bio compatible oil filter at the tank and a
secondary filter are used to protect the burner pump and nozzle from
contamination. The filter sizes must be in line with the technical manual supplied
with the burners.
6. The burner hydraulic components and flexible oil lines must be suitable for bio
fuel use (check with Riello if in doubt).
7. Regularly check visually for any signs of oil leakage from seals, gaskets and
hoses.
8. It is strongly recommended that with Bio fuel use, oil filters are inspected and
replaced every 4 months and more regularly where contamination is experienced.
9. During extended periods of non-operation and/or where burners are using oil as
a standby fuel, it is strongly recommended that the burner is put into operation for
short periods at least every three months.
Perfector 6 Side:Front
Содержание Agentis Series
Страница 2: ......
Страница 30: ...Page 29 4 5 Components 4 5 1 B Series Boilerhouse Casing Key Components...
Страница 31: ...Page 30 4 5 2 I Series Internal Casing 21 26 33 Models 44 Models...
Страница 32: ...Page 31 4 5 3 I Series Internal Key Components 21 26 33 Models 44 Models...
Страница 33: ...Page 32 4 5 4 I Series Internal Pump Group 21 26 33 Models 44 Models...
Страница 34: ...Page 33 4 5 5 I Series Internal System Components SK3 4 5 6 I Series Internal Combination Boiler Key Components...
Страница 35: ...Page 34 4 5 7 E Series External Casing 21 26 33 Models 44 Models...
Страница 36: ...Page 35 4 5 8 E Series External Key Components 21 26 33 Models 44 Models...
Страница 37: ...Page 36 4 5 9 E Series External Pump Group 21 26 33 Models 44 Models...
Страница 39: ...Page 38 4 5 12 Combination Boiler Pipe Layout...
Страница 41: ...Page 40 5 1 2 I Series Internal I21 I26 I33 5 1 3 I Series Internal I44...
Страница 42: ...Page 41 5 1 4 I Series Internal Combination Boilers I21C I26C I33C 5 1 5 E Series External E21 E26 E33...
Страница 43: ...Page 42 5 1 6 E Series External Base Tray E21 E26 E33 5 1 7 E Series External E44...
Страница 44: ...Page 43 5 1 8 E Series External E44 Base Tray 5 1 9 E Series External Combination Boilers E21C E26C E33C...
Страница 45: ...Page 44 5 1 10 E Series External Combination Boiler Base Tray E21C E26C E33C...
Страница 60: ...Page 59 6 3 2 Wiring Diagram Fuses The appliance must have a permanent live supply connected to operate...
Страница 61: ...Page 60 6 3 3 External 230V Two Channel Programmer Room Thermostat Optional Outdoor sensor...
Страница 62: ...Page 61 6 3 4 Internal Two Channel Programmer and Room Thermostat Optional Outdoor Sensor...
Страница 73: ...Page 72 6 6 9 Honeywell Y Plan Independent CH DHW Fully Pumped Only 2 CHANNEL TIMECLOCK...
Страница 74: ...Page 73 6 6 10 Honeywell S Plan Independent CH DHW Fully Pumped Only 2 CHANNEL TIMECLOCK...
Страница 93: ...Page 92 Kabin Pak External Plume Management Kit KPMK The kit comprises...
Страница 107: ...Page 106 11 4 Burner Start Up Cycle Lock out is indicated by a lamp on the control box...
Страница 122: ...Page 121 14 SPARES 14 1 RDB 2 2 BX Spares...
Страница 124: ...Page 123 14 2 RDB 3 2 BX Spares...
Страница 134: ...Page 133 Intentionally left blank...
Страница 135: ......