Commissioning
6.1
Commissioning of the drive
Read carefully the safety instructions in Chapter 1 and above and follow them.
After the installation:
Check that both the frequency converter and the motor are grounded.
Check that the mains and motor cables comply with the requirements given in
chapter 4.
Check that the control cables are located as far as possible from the power cables,
see chapter 4.4.
Check that the shields of the shielded cables are connected to protective earth
marked with
.
Check the tightening torques of all terminals.
Check that the wires do not touch the electrical components of the drive.
Check that the common inputs of digital input groups are connected to +24V or
ground of the I/O terminal.
Check the quality and quantity of cooling air.
Check the inside of the frequency converter for condensation.
Check that all Start/Stop switches connected to the I/O terminals are the in Stop-
position.
Before connecting the frequency converter to mains: Check mounting and condi-
tion of all fuses and other protective devices.
Содержание 20 CP
Страница 1: ...vacon 20 cp ac drives installation Technical and Maintenance manual ...
Страница 2: ......
Страница 6: ...vacon 3 ...
Страница 16: ...1 vacon 13 Safety Figure 6 STO certificate ...
Страница 18: ...1 vacon 15 Safety ...
Страница 24: ...vacon 21 Receipt of delivery 2 ...
Страница 36: ...3 vacon 33 Mounting ...
Страница 48: ...4 vacon 45 Power cabling ...
Страница 64: ...5 vacon 61 Control unit ...
Страница 111: ...Safe Torque Off vacon 108 Service support find your nearest Vacon service center at www vacon com 9 ...