9
Installing the Equipment
2.2
Rack Mounting the TSBC3000 Series Standalone or the
TSBC3000 Series 1+1 System
The TSBC3000 series equipment is mounted on a customer provided equipment rack using the
mounting hardware packaged in the box.
2.2.1
Prerequisites
To rack mount the equipment, you will need:
•
One 19” customer-provided equipment rack. The rack must be solidly anchored to the floor with
appropriate support at the top of the racks.
•
Climate controlled room: 0 to +70 Celsius, 0 to 95% non-condensing humidity.
2.2.2
Vertical Placement of the Equipment
The TSBC3000 series standalone, TSBC3000 1, and 1+1 Patch Panel are each housed in a 1U
chassis, as tabulated in
9. It is important that you provide for enough room on the
equipment rack to allow for the installation of the equipment.
Consider the available space on your equipment rack and the height of the TSBC3000 series
equipment. Due to the rear-exhaust heat vents and the efficient heat dissipation design, there is no
need to leave any physical vertical space above or below the TSBC3000 series equipment on the
equipment rack.
Note
The patch panel can be installed behind the TSBC3000 if the equipment rack is deep
enough. Doing so will simplify cabling.
Table
2.2
TSBC3000 Series Physical Height
Model Number
Vertical Height
TSBC3000 series standalone
1U (1.75 inches or 44.45 mm)
TSBC3000 1
1U (1.75 inches or 44.45 mm)
Patch Panel (one or two)
1U (1.75 inches or 44.45 mm)
Содержание TSBC3000
Страница 1: ...Installation Guide TSBC3000 Session Border Controller August 31 2016...
Страница 41: ...35 Installing the Equipment 3 Select a host from the Host Configuration List 4 Select the Status tab...
Страница 50: ...TSBC3000 Series Standalone and TSBC3000 Series 1 1 System Installation Guide 44...