7.5
Commissioning Assistant 2.0
The installer is required to complete the commissioning process to ensure a correct
operation of the system. During the commissioning process the installer must provide
customer related information as well as set appropriate grid parameters.
The storage system is only ready for operation if the
commissioning assistant is fully completed.
7.5.1
Establishing connection to the storage system
Please ensure that your commissioning device and the sonnenBatterie are both
connected to the same local network.
7.5.2
Running the commissioning assistant
Run the commissioning assistant until it is fully completed.
The commissioning assistant must be completed to use the
storage system.
Figure 41: Identifying the storage system
1. Step
Navigate to the following internet
address:
Select the storage system to be
configured and click on the Configure
Assistant 2.0 button
Figure 42: Logging in to the storage system as Installer
2.Step
Log in as Installer. Use the initial
password that is printed on the type
label
After a successful login you will be
prompted to change the password
In case the login fails, please contact
the sonnen service team