Installation Guide
Page 43 of 53
7
Operation of the system
7.1
Startup procedure
Figure 39: Startup procedure
To turn the system on, please follow the sequence below:
1.
Switch on the BESS Main Switch located in the switchboard
2.
Switch on the Main Switch for backup supply located in the switchboard or
dedicated subboard
3.
Switch on the BESS AC isolator adjacent to the system (if available)
4.
Switch on the BESS Backup isolator adjacent to the system (if available)
5.
Switch on the BESS using the green power button located on the left side of the
enclosure
Notice: ON position is extended OUT!
7.2
Shutdown procedure
Figure 40: Shutdown procedure
To turn the system off, please follow the sequence below:
1.
Switch off the BESS using the green power button located on the left side of the
enclosure
Notice: OFF position is pushed IN!
2.
Switch off the BESS AC isolator adjacent to the system (if available)
3.
Switch off the BESS Backup isolator adjacent to the system (if available)