6 Hydraulic connection
6 Hydraulic connection
6.1 General information
Install filter upstream
Fit an upstream filter (<25 microns) to prevent particles
from getting into the plate heat exchanger (condenser).
Check
þ
þ
Transport lock removed?
(only required
for K 12 and K 15)
6.2 Connect condensate drain
►
Plug the hot air fan
1
into the ignition pipe and
secure it using the hose clamp
2
.
Fig. 2-25_005BG
Seal the drain
►
Seal the empty space between drain hose
1
and
drain pipe
2
, e.g. with adhesive tape (used to pre-
vent rising damp).
Fig. 2-26_004-iAM-009BG
6.3 Flushing the heating circuit lines
►
Thoroughly flush the heating circuit to remove
impurities (e.g. chips, deposits).
6.4 Install the primary circuit circulation
pump
vamp
air
K 08, K 10:
Wilo-Yonos PARA (iPWM
pump)
vamp
air
K 12, K 15:
Wilo-Stratos PARA
–
The flow sensor
1
must be installed upstream of
the circulation pump when viewed in the direction
of flow.
–
The calming section
2
before and after the flow sen-
sor must not be removed.
►
Connect the primary circuit circulation pump elec-
trically
►
Connect the flow sensor electrically
6.5 Connect heating circuit
There are two options for connecting the heating circuit
line to the heat pump:
–
Inlet from the heat pump
bottom
, (from the con-
crete foundation) with the
connection set bottom
–
Inlet from the heat pump
bottom
, (from the con-
crete foundation) with the
connection set bottom
Both solutions are described in detail below.
!
CAUTION
- Due to the oscillating bearing of
the heat pump unit, the connection of the hea-
ting circuit must not be carried out as a rigid
connection.
!
CAUTION
- The connection of the heating cir-
cuit must not be carried out with stainless steel
corrugated pipes (material not suitable).
Installation manual
vampair
17
Содержание vampair K 08
Страница 25: ...7 Electrical connection Installation manual vampair 25 7 4 Electrical connection plan...
Страница 33: ...9 Foundation plan Installation manual vampair 33 Side view of foundation Section A A Fig 2 46...
Страница 34: ...Side view of foundation Section B B Fig 2 47 Detail B Fig 2 48 9 Foundation plan 34 Installation manual vampair...