IT
ALIANO
ENGLISH
20
IOMMASGPXX00-GB_01
Green Power
100-120 kVA
UNPACKING AND INSTALLATION
4
4.4.3-2
BATTERY STRING No. 1.
B1−
B1−
B1+
B1+
4.4.3-3
BATTERY STRING No. 2.
B2−
B2−
B2+
B2+
4.4.3 EXTERNAL BATTERY CABINET connection.
WARNING!
Before carrying out any operation, ensure that:
• the battery fuses located inside the battery cabinet are open;
• the UPS is not live and all mains or battery switches are open;
• the switches upstream of the UPS are open.
Use double insulated cables or the cables supplied with the unit to connect the UPS to the Battery
cabinet.
Cabling errors with inversion of the battery polarity may cause permanent damage to the equip-
ment.
If using cabinets not supplied by the manufacturers of the UPS, it is the installer’s responsibility
to check the electrical compatibility and the presence of appropriate protection devices between
the UPS and the battery cabinet (fuses and switches of suffi
cient capacity to protect the cables
from the UPS to the battery cabinet). As soon as the UPS is switched on (before closing the bat-
tery switches) the battery parameters must be verifi ed accordingly (voltage, capacity, number of
elements, etc.) on the mimic panel menu. If the values indicated on the battery cabinet data plate
are diff erent from those shown on the mimic panel, use the
SERVICE
>
CONFIGURATIONS
menu
to correct the settings.
Note.
In the case of external batteries, the minimum number of elements permissible is 20 per branch.
4.4.3-1
Содержание Green Power 100
Страница 1: ...INSTALLATION AND OPERATING MANUAL Green Power 100 120 kVA ...
Страница 2: ......
Страница 42: ...ITALIANO ENGLISH 42 IOMMASGPXX00 GB_01 Green Power 100 120 kVA MIMIC PANEL 6 6 4 1 6 6 4 1 8 6 4 1 7 6 4 1 9 ...
Страница 64: ...FRANÇAIS ...