Use cable ties to fasten the cabinet connecting cables in the bottom
part of the cabinet to the cable clamp rails
1 .5
.
Ensure that the cables are not crushed or damaged in the process.
26
Use patch cables
7 .4
to connect the LAN connection point
9
of the
SMA HV APU to one of the two switches supplied
8
via the jack
labeled “LAN.” This switch is connected to the “LAN-2” jack of the
SMA Inverter Manager and will henceforth be referred to the “LAN-2
switch.” The STPS 60-10 will also still be connected to it (see section “7
Connection to the Sunny Tripower Storage 60“ on page 28 et seq.).
27
Only for master/slave systems:
Run the CAN bus cabling between the “CAN OUT”
7
and “CAN IN”
connections
6
on the APUs of the storage systems in the master/slave configuration in accordance with the
specifications in section “5.5 Battery module wiring“ on page 17 et seq. Use the patch cable(s)
7 .4
from the
scope of delivery of the slave storage system.
28
Finally, fill out the commissioning protocol. you will find a template for this on the TESVOLT USB drive
18
. Also
document the serial numbers of the battery inverter and the peripheral devices such as the
SMA Inverter Manager. Send the completed commissioning protocol to the SMA Service center.