35
PTO DRIVE SYSTEM
The PTO drive pillow block bearings
39
should be
greased once a week or every 30 hours of operation.
Do not over lubricate, one to two pumps from a hand
operated grease gun is sufficient. CTMW uses lithium
based high temperature grease. See manufacturer’s
literature on spherical roller bearings section.
The universal crosses
44
should be greased once a
month. Do not over lubricate, one pump from a hand
operated grease gun is sufficient. CTMW uses an
aluminum complex based all- purpose grease. The slip
yoke should be greased once a year. Internal bearings in
the belt idler pulley assemblies are sealed for life and can only be replaced. A machine shop with a bearing
press may be necessary. Do not over tighten the PTO drive belts as this may cause premature bearing failure.
VACUUM SYSTEM
The vacuum fan wheel shaft bearings
41
should be greased once a week or every 30 hours of operation. Do
not over lubricate, one to two pumps from a hand operated grease gun is sufficient. CTMW uses lithium based
high temperature grease. An equivalent no. 2 consistency lithium based grease can be substituted. Also, see
manufacturer’s literature on taper roller bearings in the manufacturer’s literature section.
Clean out any material build up inside the vacuum housing
31
. Use water to soften the material to easily
wipe out. Check the exit transition
9
for material build up. Do not do any grinding to clean the wheel or
remove any weld build up.
SHREDDER BELT IDLER
Once weekly, grease shredder belt flat face idler
42
.
This is a needle bearing assembly with no seal. One
pump from a hand operated grease gun is sufficient.
CTMW uses an aluminum complex based all-purpose
grease. Wipe off excess grease to keep belts clean.
Also, do not over tension the belts. You will pre load
the shredder shaft causing premature bearing failure
and/or cause shaft breakage.
41
46
31
39
39
44
42
Содержание CertainTeed Volu-Matic 500
Страница 6: ...6 Introduction...
Страница 24: ...24 Preventive Maintenance...
Страница 38: ...38 Troubleshooting...
Страница 42: ...42 Parts Drawings...
Страница 57: ...57...
Страница 61: ...61 Preventive Maintenance Record DATE JOB DESCRIPTION PERFORMED BY...