OPERATING INSTRUCTIONS
4618-021
67
QA INSPECTOR MODE (OPTION)
(Default security code = 0004)
Introduction
The performance validation routine (PVR) helps the
users comply with ISO 9000 and BS5750 by ensuring
that the detector system is tested and operating to the
users specified quality assurance (QA) standards of
performance.
The quality standards of many user companies
require the detector and its reject system to be
manually tested at specified intervals by authorised
QA personnel to validate compliance.
QA personnel may programme the detector to
indicate when testing is required and to give an alarm
if testing is not carried out at the appropriate time.
Individual QA personnel may be allocated a personnel
security code which would be used to ensure that the
individual responsible for testing does so at the
specified time.
NOTE
Remember to record all settings on the Settings
Sheets at the rear of the manual.
Printer
Although effective as a feature in its own right the
PVR is most effective when used in conjunction with a
printer; the printer will provide a date and time
stamped hard copy print out showing when the
detector was tested and by whom.
The hard copy print out can be used to demonstrate
authorised personnel’s compliance with company
standards and hence the user companies compliance
with the agreed quality standard. This may prove
invaluable to companies wishing to demonstrate
compliance with the ISO 9000, BS5750, the UK Food
Act, and for users supplying the major retail
organisations with strict detector standards.
The printer also records general information relating
to the detector performance, it will date and time
stamp events such as rejections and changes made
to the detector settings. The printer is a very useful
management tool for recording events that affect
detector performance.
Refer to Appendix C for illustrations of typical
printouts.
Содержание Signature
Страница 16: ......
Страница 26: ...INSTALLATION 10 4618 021 Fig 5 Typical Metal Detector Conveyor ...
Страница 31: ...INSTALLATION 4618 021 15 Fig 10 Cable Gland Assemblies for Power Supply Unit ...
Страница 52: ...OPERATING INSTRUCTIONS 36 4618 021 Fig 14 Supervisor Mode Flow Chart ...
Страница 55: ...OPERATING INSTRUCTIONS 4618 021 39 Fig 15 Engineer Mode Flow Chart ...
Страница 71: ...OPERATING INSTRUCTIONS 4618 021 55 Fig 16 Pack Sensor Mode Flow Chart ...
Страница 82: ...OPERATING INSTRUCTIONS 66 4618 021 Fig 18 QA Inspector And Operator Flow Chart ...
Страница 92: ...OPERATING INSTRUCTIONS 76 4618 021 Fig 19 Viewing Mode Flow Chart ...