INSTALLATION
Installation Instructions for SIS Bus Bar Systems A2MS001EN revision R05
50 / 130
4.7
INSTALLING CONNECTION
SLEEVES
Installation information
…………………
All the dimensions specified in the drawings must be
adhered to prevent insulation damage. Vertical
connection sleeves must be supported by an insulated
bracket. If the dimensions from drawings cannot be
adhered, the procedure must be discussed with RITZ
Instrument Transformers GmbH with regard to
possible deviations, before installing the connection
sleeves. Changes must be documented.
Before closing the connection sleeves, the bus bar
system must be correctly aligned.
4.7.1
INSTALLING INDOOR
CONNECTION SLEEVES
Fill out the check list for indoor connection sleeves for
each indoor connection sleeve, see Appendix H on
page 129.
4.7.1.1
PREPARING INDOOR
CONNECTION SLEEVES
4.7.1.1.1
PREPARATION ON BOTH
SIDES
Required tools and components
………
Fig. 25: Overview of the individual parts
The following tools are required for installation:
Spanner 13 mm
Torque spanner (calibrated) socket insert 13 mm
The following components are required:
Flanges
O-ring
Bolts and washers
Flat seal (rubber seal)
Preparing the flange connections
…….
The flanges with O-ring and seal have to be placed on
the bus bar before installation of the connection
sleeve.