THE SIS BUS BAR SYSTEM
Installation Instructions for SIS Bus Bar Systems A2MS001EN revision R05
9 / 130
1.2
OTHER APPLICABLE
DOCUMENTS
In addition to these instructions, the following supplementary
documents apply:
Bill of material for installation
Installation drawings
– Assembly drawing (complete system with item numbers
and bill of material)
– Subassembly drawings
– Bus bar drawing
– Part drawings
– General detailed drawings
Optional: Specific project documents
Packing list for inspection
– packing check list
Tool list
Check list for inspecting installation one SIS bus bar system
Check list for storing and opening of one transport box
Check list for one indoor connection sleeve
Check list for one outdoor connection sleeve
If special constructions, such as wall penetrations,
transformer protection boxes, tab off boxes etc., are
required for a project, the corresponding installation
instructions or installation drawings are included with
the delivery, as necessary.
1.3
SCOPE OF DELIVERY
The construction of the bus bar system is specific to
the respective project and the individual
subassemblies can be seen in the assembly
drawing.
Refer to the subassembly drawings and part
drawings in the documentation folder for details of
individual subassemblies.
Refer to the bill of material in the documentation
folder for the exact scope of delivery.
Assigning the material
……………..…
All the items listed in the bills of material are
packaged separately with the respective item
numbers and can thus be easily assigned to the
respective positions using the bill of material for
installation.