1
3
4
2
5
PUM_SBT_091102_EN
24/38
HOSE/Grabber® INSTALLATION PROCEDURE
1.
SBT-track height over floor
(minimum 3500mm / 11,5 ft)
2.
Hose connection
3.
Hose loop height
4.
Grabber
®
nozzle height over floor
5.
Hose saddle
a) The SBT-track height (1) is a major factor in determining
the hose loop height (3)
b) The hose connection (2) location also affects the loop
height. (also see Trimming procedure)
c) Hose loop height (3) should not be less than 2,0m /
6,5ft not to be in the way of fire personnel
d) The hose saddle (5) should be placed in about half the
distance between the Grabber
®
nozzle and hose
connection
e) The distance between the floor and the Grabber
®
nozzle
(4) must be approx 250mm / 10”
8.
INSTALLATION
WARNING
PRODUCT MAY CONTAIN SHARP EDGES
Use care when servicing unit. Failure to do so could
result in minor personal injury.