Lubrication Work Center
18
IMPORTANT:
•
Write the installation date on each spin-on filter element. The first filter should be replaced after the
first 50 hours of system service. Subsequent filters should be replaced per the instructions in the
Maintenance Section of this manual, on page 28.
STEP 19.
Install the Static Discharge Grounding Reel securely to the front face of the Tank Pod (Pod-1) frame using the
threaded holes provided in theframe and the mounting bolts supplied with the reel.
STEP 20.
Pull the grounding cable out to determine if the tension is sufficient for the intended use.
a.
If additional tension is needed, apply a wrench to flats on the mainspring shaft, rotating counter-
clockwise until the desired tensionis reached.
b.
If mainspring tension is too high, it may be decreased by depressing the tension lock spring on the opposite
side of reel.
DO NOT
removemore tension than desired. If too much tension is removed, increase tension as
described above.
STEP 21.
Install the dispensing faucets supplied with your system into the threaded ports provided on the front face of the
control panel.
Use of appropriate thread sealant is recommended on threaded joints.
STEP 22.
Remove the drip pan from the packaging. Place the flange of the drip pan over the bottom horizontal support
beam at the front of the system. The drip pan rests on the beam and does not need to be fastened to the frame.
FIGURE 11a: Installing Drip Pan
FIGURE 11b: Final Drip Pan Position
Содержание Advanced Bulk System
Страница 7: ...Advanced Bulk System 7 FIGURE 1 Electric Tank Pod Pod 1...
Страница 8: ...Lubrication Work Center 8 FIGURE 2 Pneumatic Tank Pod Pod 1...
Страница 42: ...Lubrication Work Center 42 Notes...
Страница 43: ...Advanced Bulk System 43 Notes...