Figure 7. Rack-mount, 19", front-securing
4.1.3.2. 2-Post Rack-Mount, 19" And 23"
For 2-post rack installations (i.e. using the NUVP-SSG-RB-19-2P or NUVP-SSG-RB-23-2P)
1. Install one pair of brackets (i.e. both front or both rear brackets) on the posts at the desired
location.
2. Install the other pair of brackets on the Stack Switchgear.
3. Have one person support the Stack Switchgear in the desired position.
4. Attach the Stack Switchgear (with brackets installed) to the posts.
Figure 8. Rack-mount, 2-post, 19"
Nuvation Energy High-Voltage BMS - Product Manual
Document ID: NE-PM-003
13
Rev 1.2, 2021-03-03
Curie Update 1