NDA-24299
CHAPTER 6
Page 151
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
STEP 3:
Dial a telephone number (STN B) that belongs to another node.
STEP 4:
The call terminates on STN B.
STEP 5:
Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 6:
Replace the handset of STN A.
STEP 7:
Repeat the above steps for all Fusion links.
3.1.2
FCCS Call Termination Test
STEP 1:
Using the MBCT command, make busy all trunks in the origination route except the trunk to be tested
at Node B.
STEP 2:
Lift the handset of STN B in Node B.
STEP 3:
Dial a telephone number (STN A) that belongs to the self-node.
STEP 4:
The call terminates on STN A.
STEP 5:
Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 6:
Replace the handset of STN B.
STEP 7:
Repeat the above steps for all Fusion links
.
Figure 6-8 Station-to-Station Connection Test (origination) via FCCS
3.2 ATTCON Connection Test (via FCCS)
Perform the ATTCON connection test by following the procedures below and by referring to
Check
LC
LC
RG
FC CS
STN A
STN B
N ode A (Self-N ode)
N ode B
....
.
.....
C all Origination
B ch: busy
B ch: busy
B ch: busy
B ch: idle
M BC T C om m an
d
0: M ake idle
1: M ake B usy
(Make Busy Inform ation)
LS TN : 410000
STN : 2000
LSTN : 420000
S TN: 2000
Dial LSTN
"420000"
R
I N G
I N G
Note:
Using the MBCT command, make busy all B-channels in the route except the trunk to be tested.
Содержание NEAX 2400 IPX
Страница 1: ...OCTOBER 2000 NEC America Inc NDA 24299 ISSUE 1 STOCK 200776 Fusion Network System Manual ...
Страница 15: ...LIST OF TABLES NDA 24299 Page x Revision 1 0 This page is for your notes ...
Страница 73: ...CHAPTER 4 NDA 24299 Page 58 Revision 1 0 This page is for your notes ...
Страница 159: ...CHAPTER 5 NDA 24299 Page 144 Revision 1 0 DATA PROGRAMMING Office Data Sheets This page is for your notes ...