5 Mounting
Maschinenfabrik Reinhausen GmbH 2015
66
4427410/00 EN
OILTAP® R
2.
Screw on-load tap-changer head cover using screws and safety ele-
ments.
Figure 60: On-load tap-changer head cover
Drying the on-load tap-changer
1.
Connect pipe connections R and Q of on-load tap-changer head to the
kerosene vapor lead using one shared lead.
2.
Seal off unused pipe connections with a suitable blank cover.
Figure 61: Shared lead
Vapor-phase drying in the transformer tank
1.
Supply kerosene vapor at a temperature of around 90 °C. Keep this
temperature constant for 3 to 4 hours.
2.
Increase the kerosene vapor temperature by approx. 10 °C/hour to the
desired final temperature (125 °C maximum on the on-load tap-chang-
er).
3.
Vacuum dry on-load tap-changer at between 105 °C and maximum 125
°C for at least 50 hours.
4.
Residual pressure of no more than 10
-3
bar.
Closing kerosene drain plug
1.
Remove diverter switch insert.
2.
Close kerosene drain plug with extended socket wrench by turning
clockwise (tightening torque 20 Nm).
5.2.6.2.4
5.2.6.2.5
Содержание OILTAP R
Страница 1: ...On Load Tap Changer OILTAP R Installation and Commissioning Instructions 4427410 00 EN ...
Страница 123: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2015 123 4427410 00 EN OILTAP R 3 Open terminal box Figure 154 Terminal box ...
Страница 149: ...5 Mounting Maschinenfabrik Reinhausen GmbH 2015 149 4427410 00 EN OILTAP R Figure 188 Drive shaft with cardan joint ...
Страница 204: ......
Страница 205: ......