Dimensions and Clearances
– continued
JAN 2002
2-11
SC
300 1X BTS Hardware Installation, ATP, and FRU Procedures
DRAFT
Unit Clearances
The unit clearances are shown below in Figure 2-3 through Figure 2-7.
Figure 2-3: Installation and Functional Clearances for MicroCell Units (Without Solar Covers)
50 mm air exhaust area
100 mm clearance for installation handles
200 mm clearance for tool access
50 mm air intake area
50 mm air intake area
600 mm from front of unit for FRU
installation and removal
Figure 2-4: Installation and Functional Clearances for MicroCell Units (With Solar Covers)
50 mm air exhaust area
50 mm air intake area
100 mm clearance for installation handles
200 mm clearance for tool access
600 mm from front of unit for FRU installation and removal
0 mm Functional Clearance in Front of
Microcell With Solar Cover
2
Содержание SC 300
Страница 30: ...Table of Contents continued DRAFT SC 300 1X BTS Hardware Installation ATP and FRU Procedures JAN 2002 Notes 1 ...
Страница 60: ...Table of Contents continued DRAFT SC 300 1X BTS Hardware Installation ATP and FRU Procedures JAN 2002 Notes 2 ...
Страница 76: ...Table of Contents continued DRAFT SC 300 1X BTS Hardware Installation ATP and FRU Procedures JAN 2002 Notes 3 ...