363-208-010
Installation Procedures
Issue 5
May 1997
2-11
Mounting System Shelves
NOTE
:
These procedures shall be followed when separate shelves must be
mounted, when increasing system capacity, or when equipment shelves
must be replaced. Refer to the Figure 2-5 or 2-7 for equipment shelf loca-
tions.
NOTE
:
RT Frames may have been pre-assembled at an Lucent Technologies Ser-
vice Center with a complement of shelves in accordance with an engi-
neered order or may have only a minimum complement of shelves
equipped. In either case the customer’s order should be checked for the
correct configuration of shelves. RT frames coded J1C265A-1 may have
been ordered from the supplier as a complete complement of shelves, fac-
tory mounted and interconnected.
NOTE
:
Shelves must be assembled only in accordance with the Mounting Hole
Locations in Figure 2-5 or 2-7. To mount the shelves otherwise would
destroy the integrity of the system airflow, the local cable connections and
the growth pattern.
NOTE
:
Before attaching the shelf’s ground wire to the bay frame, remove as much
of the frame’s paint as necessary to ensure a low-resistance ground and
apply an oxidation preventative such as NO OX-ID “A”.
Содержание SLC-2000 Access System Central Office Terminal
Страница 1: ...SLC 2000 Access System Customer Assembly Manual for RT Frames 363 208 010 Issue 5 May 1997...
Страница 4: ...This page is intentionally blank...
Страница 10: ...viii Issue 5 May 1997 Contents...
Страница 16: ...xiv Issue 5 May 1997 Tables...
Страница 24: ...1 ii Issue 5 May 1997 Contents General Information...
Страница 34: ...2 iv Issue 5 May 1997 Tables Installation Procedures 2 1 Dimensions for Figure 2 2 6...
Страница 66: ...3 viii Issue 5 May 1997 Contents Cabling Wiring and Assembly...