Help Hot Line (U.S. only): 1-800-530-9960
7-21
D-620003-0-20 Rev J
CONFIDENTIAL
Unison Component Installation Procedures
2.
Connect “red” to
UPLINK
on Expansion Hub.
The
UL STATUS
LED turns green on the first Main Hub communication. It may
take up to 20 seconds to establish communication.
The Expansion Hub’s
E-HUB STATUS
LED turns green when the Main Hub sends
it the frequency band command.
If the
UL STATUS
and
E-HUB STATUS
LEDs do not turn green/green, check the
Main Hub LEDs. See page 7-16, item 2 in Table 7-5.
Connecting the ScTP Cables
Consideration:
• Verify that the cable has been tested and the test results are recorded.
To test and connect the ScTP cable:
1.
Perform cable testing.
Test results are required for the final As-Built Document.
Cable length:
– Minimum: 10 m (33 ft)
– Recommended Maximum: 100 m (328 ft)
– Absolute Maximum: 150 m (492 ft)
If you are using a Cat-5 Extender, the cable length maximum is 170 m (557 feet).
(Refer to Section 7.4.5 on page 7-29.)
2.
Label both ends of each cable with which RJ-45 port you’re using.
3.
Connect the ScTP cables to any available RJ-45 port on the Expansion Hub.
The
LINK
and
RAU
LEDs should be off because the RAU is not connected.
4.
Record which cable you are connecting to which port.
This information is required for the As-Built Document.
5.
Tie-off cables or use the optional cable manager to avoid damaging the connectors
because of cable strain.