Page 61
C2-1 DIAGRAM WITH D5 DIAGRAM
Electromechanical Thermostat with Economizer and WarmUp
C-WARMUP KIT
An optional feature of the REMD16M economizer is a warmup kit which holds the economiz
er outdoor air dampers closed during night heat operation and while the CHA16 is warming
the building the morning after. The warm-up kit temporarily disables the economizer (outdoor
air dampers are held closed) during morning warm-up to keep cool outside air from being
mixed with return air. Once the temperature setpoint is reached, the economizer is allowed to
operate normally (outdoor air dampers open to minimum position to allow required minimum
air exchange).
NOTE-In order to understand how optional controls affect the operation of the CHA16, you
must first read and understand how all the CHA16 components work.
NOTE-
1 - The warm-up kit requires the use of optional time clock CMC3-1.
2 - Optional night thermostat S12 must be installed.
3 - The warm-up kit can only be installed in CHA16 units with REMD16 economizer.
WARNING-CONNECT ONLY RELAY KITS DESIGNED FOR THIS CONTROL SYSTEM.
RELAY KITS DESIGNED FOR OTHER CONTROL SYSTEMS ARE NOT COMPATIBLE
AND CONTROL DAMAGE OR FAILURE WILL RESULT. FOR EXAMPLE, A W973
RELAY KIT MUST NOT BE CONNECTED TO A ELECTROMECHANICAL THERMO
STAT CONTROL SYSTEM.
WARNING-BE CAREFUL TO CONNECT RELAY KITS TO THE PROPER JACK AND
PLUG IN THE CHA16 BLOWER COMPARTMENT. REFER TO WIRING DIAGRAM. IM
PROPER CONNECTION WILL CAUSE CONTROL FAILURE.
The warmup kit installs in the control mounting area of the CHA16 filter access compart
ment. No wiring is required. Jumper plug P3 is removed and discarded. Warmup kit harness
plug P8 connects directly into jack J3 in the blower compartment. Warmup kit harness jack
J8 connects to economizer harness plug P4.
Operation Sequence:
NOTE-This operation sequence emphasizes warmup kit operation. Unit diagram has
been omitted.
1 - When relay K41 is energized during normal operation, the economizer functions nor
mally and is lockedin until night setback. When relay K41 is de-energized, economiz
er is disabled.
2 - Economizer outdoor air dampers drive full closed anytime blower B3 is not operating.
Night Setback:
3 - Time clock CMC3-1 should be adjusted so that clock contacts remain closed during
hours when the building is not occupied. The contacts are set to open shortly (usually
1 hour) before the building is to be occupied.
4 - When clock contacts close, relay K11 in the economizer and K42 in the warmup kit are
energized.
5 - Contacts K11-1 open to disconnect power to thermostat S1. K11-2 open to drive the damp
ers full closed.
6 - Contacts K42-1 open to disengage relay K41.
7 - When relay K41 disengages, power is disconnected to the economizer:
a-Contacts K41-1 open to lockout economizer operation.
b-Contacts K41-2 close (not used).
c-Contacts K41-3 open to disconnect power to the economizer.
d-Contacts K41-4 open (not used).
8 - During unoccupied periods, K11-1 opens and S1 is disabled. When S12 closes, power is
returned to S1 and the unit operates (heating demand) normally. When S12s setpoint is
reached, S12 opens, S1 is disabled and unit operation stops.
9 - Blower operates only on demand energized by ECH16 heat relay K9 when S12 is closed.
10 - Thermostat S1 and economizer remain inoperable until time clock CMC3-1 contacts open.
First Heat Demand After Night Setback (Begin Warm-Up)
11 - Shortly before the building is to be occupied, time clock CMC3-1 contacts open.
12 - Relay K42 disengages and contacts K42-1 close.
13 - Relay K11 disengages. Contacts K11-1 close to allow power to thermostat S1. Contacts
K11-2 close to allow outdoor air dampers to open. Note that dampers remain closed until
relays K3 and K41 are energized.
14 - Since contacts K40-1 are normally closed and contacts K42-1 have just switched closed,
timer DL7 is energized. Timer DL7 is normally open and closes 30 sec. after being ener
gized.
15 - If heat demand W1 reaches relay K40 before delay DL7 closes, contacts K40-1 open,
delay DL7 loses power and resets and the economizer is locked-out for the first heat de
mand by relay K41 (contacts K41-3 remain open). If heat demand W1 reaches relay K40
after delay DL7 closes, relay K41 energizes and the economizer locks-in for the day until
night setback.
16 - When first heat demand is satisfied, relay K40 disengages and relay K40 contacts K40-1
close. Relay contacts K42-1 are already closed (clock contacts open). Time delay DL7 be
gins 30 sec. count. If a second heat demand W1 does not reach relay K40 within 30 sec.,
time delay DL7 contacts close and relay K41 energizes.
17 - When relay K41 energizes, the economizer is allowed to operate normally, controlled by relay
K3:
a-Contacts K41-1 closes to lockin economizer operation until night setback.
b-Contacts K41-2 open (not used).
c-Contacts K41-3 close to allow power to the economizer.
d-Contacts K41-4 close (not used).
18 - Once energized, relay K41 locks-in and the economizer operates until relay K42 is ener
gized by night setback (contacts K42-1 open to disengage relay K41).
Содержание CHA16
Страница 47: ...Page 47 FIGURE 52 CYCLE CONTROL KIT WIRING DIAGRAM...
Страница 55: ...Page 55 NOTES...
Страница 58: ...C1diagram electromechanical thermostat with modulating economizer with D5 diagram Page 58...
Страница 60: ...C2 1 diagram electromechanical thermostat with modulating economizer and warm up with D5 diagram Page 60...
Страница 62: ...Page 62 B41 diagram with C1 diagram CHA16 2553 2753 3003 Operating Sequence...
Страница 64: ...Page 64 B9 diagram with C1 diagram CHA16 1853 Operating Sequence...