7-46 Keysight N5247B Service Guide
Repair and Replacement Procedures
Removing and Replacing the A33–A36 Test Port Couplers
7-
Removing and Replacing the A33–A36 Test Port Couplers
Tools Required
— T-10 TORX driver (set to 9 in-lb)
— T-20 TORX driver (set to 21 in-lb)
— 5/16 inch open-end torque wrench (set to 10 in-lb)
— 1 inch open-end torque wrench (set to 72 in-lb)
— ESD grounding wrist strap
Removal Procedure
Refer to
for this procedure.
1.
Disconnect the power cord.
2.
Remove the front panel assembly. Refer to
Front Panel Assembly” on page 7-8
.
3.
Position the analyzer bottom side up.
4.
On 4-port models, it is necessary to remove the couplers in pairs: ports
1/3 and 2/4.
5.
Disconnect two semirigid cables (item
) from each coupler to be
removed.
6.
Disconnect the wire harness (item
) from the corresponding front panel
LED board and place it out of the way.
7.
Remove the coupler nut (item
) from each coupler to be removed.
8.
Move the disconnected semirigid cables out of the way and remove the
coupler(s) from the analyzer. It may be necessary to loosen the connector
at the other end of some of the semirigid cables to allow them to be
moved enough.
Replacement Procedure
1.
Reverse the order of the removal procedure.
Adhere a new gap pad (4-port) or coupler bumper (2-port) (item
) to the
new coupler in the same location as on the old one. If necessary, replace
the vibration mount (item
). Refer to
Miscellaneous Parts” on page 6-196
for replacement part numbers.
Be careful not to damage the center pins of the semirigid cables. Some
flexing of the cables is necessary to remove the assembly. However, do not
over-bend the semirigid cables.
Содержание N5247B
Страница 10: ...10 Keysight N5247B Service Guide Contents ...
Страница 96: ...3 66 Keysight N5247B Service Guide Tests and Adjustments Adjustments 3 ...
Страница 157: ...Keysight N5247B Service Guide 4 61 Troubleshooting This page left intentionally blank ...
Страница 227: ...Keysight N5247B Service Guide 5 57 Theory of Operation Receiver Group Operation Figure 5 18 4 Port Receiver Group ...
Страница 228: ...5 58 Keysight N5247B Service Guide Theory of Operation Receiver Group Operation 5 Figure 5 19 2 Port Receiver Group ...
Страница 238: ...5 68 Keysight N5247B Service Guide Theory of Operation Noise Measurement Group Operation Option 029 5 ...
Страница 243: ...Keysight N5247B Service Guide 6 5 Replaceable Parts Rebuilt Exchange Assemblies Figure 6 1 Module Exchange Procedure ...
Страница 268: ...6 30 Keysight N5247B Service Guide Replaceable Parts Replaceable Parts Listings 6 ...
Страница 270: ...6 32 Keysight N5247B Service Guide Replaceable Parts Replaceable Parts Listings 6 ...
Страница 373: ...Keysight N5247B Service Guide 6 135 Replaceable Parts Replaceable Parts Listings ...
Страница 381: ...Keysight N5247B Service Guide 6 143 Replaceable Parts Replaceable Parts Listings This page intentionally left blank ...
Страница 426: ...6 188 Keysight N5247B Service Guide Replaceable Parts Replaceable Parts Listings 6 ...
Страница 548: ...7 104 Keysight N5247B Service Guide Repair and Replacement Procedures Post Repair Procedures 7 ...
Страница 565: ...Installation Note Xxxxx xxxxx 3 ...