1.
Carefully clean the stuffing-box bore.
2.
Twist the packing enough to get it around the shaft.
Packing rings
Lantern rings
1
3
4
2
3
4
1.
Packing rings
2.
Lantern rings
3.
Correct
4.
Incorrect
Figure 49: Packing rings and lantern rings
3.
Insert the packing and stagger the joints in each ring by 90°.
Install the stuffing-box parts in this order:
a) One packing ring
b) One lantern ring (two-piece)
c)
Three packing rings
NOTICE:
Make sure that the lantern ring is located at the flushing connection to ensure that flush is ob-
tained. Failure to do so may result in decreased performance.
4.
Install the gland halves and evenly hand-tighten the nuts .
6.8.3.3 Seal the shaft with a cartridge mechanical seal
WARNING:
The mechanical seal used in an Ex-classified environment must be properly certified.
The mechanical seal must have an appropriate seal flush system. Failure to do so will result
in excess heat generation and seal failure.
CAUTION:
Running a mechanical seal dry, even for a few seconds, can cause seal failure and physical
injury. Never operate the pump without liquid supplied to the mechanical seal.
1.
Before proceeding with seal installation, complete Steps 1-30 in
6.8.3.1 Shim measurement method
.
NOTICE:
Reference Cartridge seal installation instructions.
2.
Remove casing cover (161) from frame adapter (344).
3.
Slide the cartridge seal onto the shaft or sleeve until it contacts the inboard labyrinth oil seal.
6.8 Reassembly
90
Model ICO i-FRAME, ICOH i-FRAME Installation, Operation, and Maintenance Manual
Содержание GOULDS PUMPS ICO i-FRAME
Страница 1: ...Installation Operation and Maintenance Manual Model ICO i FRAME ICOH i FRAME ...
Страница 2: ......
Страница 104: ...8 1 Parts list 102 Model ICO i FRAME ICOH i FRAME Installation Operation and Maintenance Manual ...
Страница 105: ...8 1 Parts list Model ICO i FRAME ICOH i FRAME Installation Operation and Maintenance Manual 103 ...