Start the pump
WARNING:
Risk of equipment damage, seal failure and breach of containment. Ensure all flush and cooling
systems are operating correctly prior to starting pump.
NOTICE:
• Risk of equipment damage due to dry operation. Immediately observe the pressure
gauges. If discharge pressure is not quickly attained, stop the driver immediately, reprime,
and attempt to restart the pump.
• On frame mounted units, ensure that the oil level is correct prior to starting pump. Close
coupled pumps do not have oil lubricated bearings.
NOTICE:
Risk of equipment damage on pure or purge-oil mist-lubricated units. Remove the viewing port
plugs to verify that oil mist is flowing properly. Reinstall the plugs after confirming.
Before you start the pump, you must perform these tasks:
• Open any recirculation or cooling lines.
• Start the external bearing flush, if specified.
• Make sure the shaft rotates freely.
1. Fully close or partially openthe discharge valve, depending on system conditions.
2. Start the driver.
3. Slowly open the discharge valve until the pump reaches the desired flow.
4. Immediately check the pressure gauge to ensure that the pump quickly reaches the correct
discharge pressure.
5. If the pump fails to reach the correct pressure, perform these steps:
a) Stop the driver.
b) Prime the pump again.
c) Restart the driver.
6. Monitor the pump while it is operating:
a) Check the pump for bearing temperature, excessive vibration, and noise.
b) If the pump exceeds normal levels, then shut down the pump immediately and correct
the problem.
A pump can exceed normal levels for several reasons. See Troubleshooting for
information about possible solutions to this problem.
7. Repeat steps 5 and 6 until the pump runs properly.
Содержание Goulds Pumps API 3171