l
If the dialup is successful, go to
.
l
If the dialup fails, go to
7.
In ETH mode, run the
display port state portid
command to check whether the duplex
mode, rate, network cable adaptation mode of the Ethernet port are consistent with those
of the user terminal.
l
l
If they are inconsistent, modify the parameter settings of the Ethernet port to ensure that
the parameter settings are consistent with those of the user terminal. Then, go to
.
NOTE
In ETH mode, modify the parameter settings of the Ethernet port by using the following methods:
l
Run the
auto-neg
command to enable or disable the auto-negotiation mode of the Ethernet port.
After the auto-negotiation mode of the Ethernet port is enabled, the Ethernet port automatically
negotiates the port rate and duplex mode with the interconnected port.
l
Run the
duplex
command to configure the duplex mode of the Ethernet port to full duplex or half
duplex.
l
Run the
mdi
command to configure the network cable adaptation mode of the Ethernet port.
l
Run the
speed
command to configure the rate of the Ethernet port.
8.
Perform a dialup check.
l
If the dialup is successful, go to
.
l
If the dialup fails, go to
9.
Replace the port and perform a dialup check. Then, check whether the dialup is successful.
l
If the dialup is successful, the original user port is faulty. Change the user's port and
reconfigure the port data. Then, go to
.
l
If the dialup fails, go to
Step 4
Check whether the data configuration on the MA5612 is correct.
1.
Run the
display service-port port frameid/slotid/portid
command to check whether the
data configuration of the user's service port, such as the VLAN ID and port ID, is correct.
l
If the data configuration of the user's service port is correct, go to
l
If the data configuration of the user's service port is incorrect, go to
.
NOTE
l
Run the
undo service-port
command to delete the original service port.
l
Run the
service-port
command to configure a new service port.
2.
Perform a dialup check.
l
If the dialup is successful, go to
.
l
If the dialup fails, go to
3.
Run the
display port vlan frameid/slotid/portid
command to check whether the uplink port
was added to the upstream VLAN.
l
If the uplink port was added to the upstream VLAN, go to
l
If the uplink port was not added to the upstream VLAN, run the
port vlan
command to
add the uplink port to the upstream VLAN, whose configuration must be the same as
the configuration on the upper layer device.Then, go to
.
4.
Perform a dialup check.
l
If the dialup is successful, go to
.
SmartAX MA5612 Multi-service Access Module
Maintenance Guide
4 Troubleshooting Services Transmitted Through a GE Port
Issue 01 (2012-07-25)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
35