Procedure
Step 1 Connect the hoisting ropes and hoist the unit to the installation area.
NO TE
It is recommended that a crane with a lifting capacity greater than or equal to 15 t be used
for transportation.
Figure 5-4 Hoisting a unit
Step 2 Remove the sealing plate and bottom plate of the outdoor air exhaust vent from
the top, bottom, or end surface based on the actual scenario.
Step 3 Secure the unit on the side of the indoor air supply vent (end).
Step 4 Open the maintenance door and enter the container to secure the unit.
NO TE
Secure the unit using the actual number of bolts for fasteners.
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
5 System Installation (FDC Scenario)
Issue 03 (2021-04-20) Copyright © Huawei Digital Power Technologies Co., Ltd.
75