Installation Manual – BTS3606A Cabinet Installation
Airbridge BTS3606&3606A CDMA Base Station
Chapter 1 Installation Preparations
Huawei Technologies Proprietary
1-3
Note:
The equipment supplier provides the tool list and consults to the customer to specify
the tool provider. The wire punchdown tool is delivered along with the cabinet.
Check the meters to ensure that they are qualified for use.
1.3 Installation Conditions
The project supervisor must do the following:
z
Check the construction conditions.
z
Fill out the Installation Environment Checklist.
z
Sign the Kickoff Agreement with the customer if all conditions are ready.
z
Formulate the Project Installation Plan.
If the installation is not prepared as required, fill out the
Onsite Work Liaison Form
to
declare the reason for kickoff postpone.
If the customer needs immediate kickoff, require the time when the installation will be
prepared.
1.3.1 Site Requirements
Check the installation site with respect to its area, height and load-bearing capacity. If
the site cannot satisfy these requirements, it is advised to re-plan the engineering.
1.3.2 Load-bearing Capacity Requirements
The BTS3606A must be installed on a stable and level cement floor. The weight
capacity of the floor must satisfy the weight requirement of the cabinet. If the
BTS3606A is installed on the rooftop, the weight capacity of the rooftop must meet the
weight requirement of the cabinet.
If the installation site cannot satisfy this requirement, it is necessary to fortify it with a
cement base. The following provides the engineering requirements.
I. Cement Base of BTS3606A Single Cabinet
For the BTS3606A cabinet installation, the cement base can be made according to the
appearance and size illustrated in Figure 1-2. For the height of the cement base, the
local environmental condition must be taken into consideration. Make sure that the
cabinet will not suffer water penetration during heavy rain or flood, and in the season of