Installation Manual – BTS3606A Cabinet Installation
Airbridge BTS3606&3606A CDMA Base Station
Chapter 5 Installing Cables
Huawei Technologies Proprietary
5-44
Note:
The resistance of the grounding body must accord with the related regulation of the
country or the operator’s regulation on communication sites (or radio base station).
5.8.3 Connecting PGND Cable of the Cabinet
To connect the PGND cable of the cabinet, proceed as follows:
1)
Measure the distance between the internal ground bar of the BTS3606A and the
connector of the outdoor grounding bar according to the actual cabling path of
PGND cables.
2)
Cut PGND cables as needed.
3)
Attach temporary labels to both ends of each cable. Note that the contents of
temporary labels can be consistent with formal labels or defined by yourself.
4)
Route the PGND cables according to cabling craft requirements and engineering
requirements.
5)
Prepare PGND cables for the cabinet following the instructions in section 5.8.1
"Making Cabinet PGND Cables".
6)
Lead one end of a PGND cable into the cabinet from the inlet of the waterproof
module. Connect it to the grounding bar inside the cabinet. Fasten the OT terminal
of the PGND cable using spring washers and screws.
7)
Connect the other end of the PGND cable to the grounding copper bar (specified
by the customer) outside the cabinet.
8)
After installing PGND cables, attach corresponding labels to the points 20 mm to
50 mm away from both ends of PGND cables according to numbers.