Diagnostics
44
Edge Switch 2/12 Service Manual
4
Have the customer inspect and verify that facility power is within specifications.
These specifications are:
■
One single-phase connection for the power supply.
■
Input power between 100 and 240 VAC, and at least 5 amps.
■
Input frequency between 47 and 63 Hz.
Is facility power within specifications?
YES
NO
↓
Ask the customer to correct the facility power problem. When facility
power is corrected, continue to the next step.
5
Verify power supply and switch operation. Inspect the switch for indications of
being powered on, such as:
■
At the front bezel, an illuminated PWR LED (green) or ERR LED (amber).
■
Illuminated LEDs adjacent to Fibre Channel ports.
■
Audio emanations and airflow from cooling fans.
Is a power supply or power distribution system failure indicated?
YES
NO
↓
The switch appears operational. Exit MAP.
6
The power supply may be operational, but the CTP card is not receiving DC
power. The in-card circuit breaker may have tripped due to a power surge, or the
CTP card failed. Disconnect the power cord, then reconnect the cord (power cycle
the switch) to reset the CTP card.
Did power cycling the switch solve the problem?
NO
YES
↓
The switch appears operational. Exit MAP.
7
Visual inspection indicates a power supply, power distribution system, or CTP
card failure. Replace the switch. Exit MAP.
Содержание StorageWorks Edge Switch 2/12
Страница 16: ...About this Guide 16 Edge Switch 2 12 Service Manual ...
Страница 124: ...Repair Information 124 Edge Switch 2 12 Service Manual ...
Страница 132: ...Illustrated Parts Breakdown 132 Edge Switch 2 12 Service Manual ...
Страница 172: ...Event Codes 172 Edge Switch 2 12 Service Manual ...