76
Installing Field-replaceable units (FRUs)
Core switch blade (CR8)
This section describes how to remove and replace a core switch blade. Each DC Director integrates two
core switch blades located in slot 5 and slot 8.
The replacement procedure for the core switch blade takes approximately 30 minutes. The following items
are required for the core switch blade replacement:
•
ESD grounding strap
•
Phillips #2 screwdriver
•
Replacement core switch blade (requires the DC Director core switch blade (CR8).
How to determine whether or not to replace a CP blade
Confirm that you need to replace the core switch blade before continuing. The following events might
indicate that a core switch blade is faulty:
•
The status LED on the core switch blade is lit amber, or the power LED is not lit.
•
The
slotShow
command does not show that the core switch blade is enabled.
•
The
haShow
command indicates an error.
•
Any of the following messages display in the error log:
•
Slot unknown
message relating to a core switch blade slot
• core switch blade errors or I
2
C timeouts
•
FRU: FRU_FAULTY
messages for a core switch blade
•
Configuration loader
messages or
Sys PCI config
messages
• Generic system driver messages (
FABSYS
)
• Platform system driver messages (
Platform
)
•
EM
messages that indicate a problem with a core switch blade
• Function fail messages for the core switch blade master
For more information about error messages, refer to the
Fabric OS Message Reference
.
Содержание A7990A - StorageWorks SAN Director 4/16 Blade Switch
Страница 8: ...8 ...
Страница 27: ...DC SAN Backbone Director hardware reference guide 27 I Figure 3 14U Rack Mount Kit contents 26419a ...
Страница 62: ...62 Monitor system components ...
Страница 100: ...100 Installing Field replaceable units FRUs ...
Страница 122: ...122 Intelligent blades ...
Страница 132: ...132 Regulatory compliance and safety notices ...
Страница 134: ...134 Port numbering templates 26390a ...
Страница 135: ...DC SAN Backbone Director hardware reference guide 135 26389a ...
Страница 136: ...136 Port numbering templates 26388a ...
Страница 137: ...DC SAN Backbone Director hardware reference guide 137 FC 10 6 0 2 3 4 5 1 2 3 4 5 FC 10 6 2 3 4 5 1 1 0 0 26391a ...
Страница 140: ...140 Port numbering templates ...