Preparing the Installation
Several requirements regarding the mounting site and connection technology must be
met for the installation in order to guarantee a safe operation.
Requirements for mounting site
The cPH1 charging station was developed for indoor as well as outdoor areas. As user
please note the following requirements for the mounting site and installation to
ensure safe charging later on.
•
Follow all local regulations concerning electrical installation, fire
prevention and accident prevention
•
All regulations to installing a low voltage system according to IEC 60364-
1- and IEC 60364-5-52 apply to any times.
•
The mounting surface has to be steady and solid enough to withstand
mechanical pressure.
•
The installation position has to provide a lead big enough for the power supply.
Depending on your variant two separate leads are also possible.
•
Do not install the Wallbox at crowded areas or passage ways. Please
make sure to lay all charging cables in sight and pedestrians or routes
are NOT obstructed in any way.
•
Even though basically the cPH1 is constructed to operate in an environment
with high temperatures. If possible, it is highly recommended to install the
charging station at a place where it is protected of direct sun irradiation. This
way overheat of the housing can be prevented. You can find more
information to environmental conditions in section “Technical specifications”
on page 29.
•
The socket and storage devices for the connector should be between 0,4m and
1,5m above the ground.