39
Step D-10:
Carefully insert the power cable plug into the coupling at the bottom of the operator housing.
Turn the plug until it aligns with the pins in the operator coupling. Tighten the sleeve nut to lock
the plug into place.
NOTE: DO NOT attempt to splice the power cable, and DO NOT remove the connector
from the end of the cable. If you need a longer cable, 35 foot and 40 foot power cables are
available (see Accessory Catalog).
AUTOMATIC GATE OPENERS
®
Step D-9:
Cut slot into driveway and lay PVC conduit in this slot. Pull the 25 foot power cable for the second operator through
the conduit (see Illustration B on page 37).
Setting the Control Board for Dual Gate Installations
DIP Switches
The Control Board DIP switches must be set to accommodate your particular type of installation. Since the
SNGL / DUAL, SEQ1, and SEQ2 DIP switches are used by dual gate operator systems, they will be discussed in the
following steps.
Step D-11:
Make sure the control box power switch is OFF.
Step D-12:
Unscrew and remove the control box cover. Use a
small screwdriver to move the SNGL / DUAL DIP
switch to DUAL (see illustration).
The order of gate operation ("sequencing") must
now be determined for your dual gate operators to
function properly.
Refer to the illustrations on the next page.
NOTE: The terms "FIRST OPERATOR" and
"SECOND OPERATOR" refer to a unit wired to
the terminal block of the same name.
1234
ON
OBSTRUCT
SENS.
PULL/PUSH
SEQ1
SNGL/DUAL
SEQ2
MIN
MAX
LEARN