90
- Chapter 8 - Operation
G8 Super Cruiser Operator’s Manual MY19 - REV 0
Spray Application
After completing the filling process, you are now
ready to start spraying. While travelling from the
fill station to the field, the pump should be running
at 4000-4200 rpm on standard fitment centrifugal
pump or 400-540 rpm on optional fitment
diaphragm pump with the agitator running in order
to ensure that the chemical mix is adequately
agitated prior to spraying.
NOTE:
The following information is provided as a
guide only. It is the responsibility of the operator to
assess the conditions in the field where the spray
application is taking place
NOTE:
The main pressure station ball valve must be
in the bypass (spray mode) position.
1. Enter the field, unfold boom and set the boom to
desired height above the target and have pump
running.
2. Switch on the console and set to run in self test
mode (while stationary). Information on running
in self test mode can be found in the spray
controller operators manual supplied.
4. Purge all boom lines with product from the main
tank. Turn on boom recirculation for 2 minutes
and then off again.
5. Commence travel on primary swathe and engage
boom master switch. Auto rate controller will
now control application based on the calibration
information entered by the operator.
6. To avoid overlap it is recommended that
individual boom section switches are used to turn
on/off sections as needed.
7. When you have completed the task at hand,
please follow the flushing instructions to ensure
that all plumbing is flushed.
NOTE:
It is important that boom recirculation
is turned off before spraying. If it is left on while
spraying, the flow meter will read incorrectly leading
to the wrong amount of chemical being applied.
Agitation
TO AGITATE WHILE STATIONARY
1. Add 20 percent of the main tank’s volume in
fresh water to the main tank.
2. Add all chemicals.
3. Add the remaining quantity of water required.
4.
Turn the 3 way ball valve to Bypass, and ensure
suction handle is on ‘Suction Main Tank’.
5. Turn the agitator on.
6. Turn the spray pump on. Check to ensure that
the Supermix agitator is working. There should
be a visible circulation of water near the back of
the tank near the agitator.
7.
If the tank has been filled and the spray mixture
has been allowed to settle, agitate for as long
as it takes the pump to pump the quantity of
water in the tank. For example: with 8000 litres
in the tank with a 400 L/min pump agitate for
8000/400 = 20 minutes.
TO AGITATE WHILE SPRAYING
Have the bypass ball valve and agitator ball valves
OPEN.
NOTE:
The bypass ball valve must be open while
spraying.
Содержание Super Cruiser G8
Страница 1: ...Super Cruiser G8 Operator s Manual MY19 GA8700989 REV 0 APR 2019 FROM SERIAL 202114 ...
Страница 12: ...8 Chapter 2 Safety G8 Super Cruiser Operator s Manual MY19 REV 0 ...
Страница 18: ...14 Chapter 3 General Information Specs G8 Super Cruiser Operator s Manual MY19 REV 0 ...
Страница 34: ...30 Chapter 4 Cabin G8 Super Cruiser Operator s Manual MY19 REV 0 Power Distribution Box Fuse Box Layouts ...
Страница 43: ...Chapter 4 Cabin 39 G8 Super Cruiser Operator s Manual MY19 REV 0 CANtrak System Parameters Monitored ...
Страница 58: ...54 Chapter 4 Cabin G8 Super Cruiser Operator s Manual MY19 REV 0 ...
Страница 74: ...70 Chapter 7 Pre Operation G8 Super Cruiser Operator s Manual MY19 REV 0 ...
Страница 104: ...100 Chapter 8 Operation G8 Super Cruiser Operator s Manual MY19 REV 0 ...
Страница 210: ...www goldacres com au ...