5.9.7 Insulation test
ATTENTION:
Once the electrical system installation is complete, a ground
insulation test must be performed as follows:
1.) Switch off all on-board electrical devices.
2.) Start the generator.
3.) Measure the AC-voltage with a voltmeter (adjust to Volt/AC) between
a) generator housing and AC-Control box
b) generator housing and ground.
The measured voltage must not exceed 50mV (millivolts).
6. Once the safety systems have been installed, they must be checked. If a RCD (Leakage Current Relay) has been
installed, it also has to be tested, in order to ensure that it functions properly. The individual phrases must be
checked against each other, and between phase and ground, (the single phase or 4th phase also needs to be
checked in this fashion).
7. If the generator is protected by a ground connection, then ALL electrical devices must also be connected to this
"common" ground (usually ground contacts are attached to the devices' metallic housings).
The electrical system installation must also comply with the hook-up requirements of the shore current grid. Gene-
rally a leakage current relay is sufficient for safe electrical operation; however, this must be confirmed by the electri-
cal safety standard in the region where the system is attached to a main land power grid. The relay has to meet the
required safety standard regulations.
Checking the electrical connections
There is always the possibility that circuits have been rerouted/changed or individual components have not been not
been correctly laid out on the circuit diagrams.
The installation electrician should therefore check and label all electrical connections to ensure that they correspond
to the main circuit diagram. The inspection and correct labelling is especially critical for terminals L1/ L2/L3/L1'/N (for
the 230 V - 50 Hz model) and for terminals L1/L2/L3/N &1/ 2/ 4 for the 60 Hz (120 V) models. The electrician is the-
refore obliged, before installation to check whether the generator is earth-free. As long as this test has not been car-
ried out all other components for electrical installation must be removed. Once the system has been installed and
inspected, this test should also be performed with all electrical devices (i.e. voltage check between common and
metallic housings) while the generator is running.
Содержание 6500 PMS
Страница 58: ...The Panda Generator Seite Page 58 Panda_6500_7mini_PMS_eng R01 Kapitel Chapter 4 The Panda Generator 22 3 11 ...
Страница 168: ...Seite Page 168 Panda PMS 8 000 NE 42 NE Manual R05 22 3 11 Leere Seite Intentionally blank Generator Faults ...
Страница 214: ...Seite Page 214 Panel Generator Control P6 RE0703_Kunde_eng R06 1 22 3 11 Leere Seite Intentionally blank Measurements ...