2.1 SAFETY REQUIREMENTS
The installation of the product must be performed by authorized technicians who scrupulously follow all safety
norms and procedures – law provision N° 46/90 (Legislative March 5 1990, n° 46). Only such appointed personnel
is authorized to open the Control Panel; inside there may be parts run through voltage electricity.
The product, is Class I conforming to the EN 60950-1 Normative, must be connected to the mains power line and
maintain the grounding connection and power surge protection (PE) as described on chapter
2.2.
Where to install the product.
The product should be installed in a dry area which is not subject to weather agents. Make sure that sufficient
space is left around the control panel box so that some ventilation is guaranteed. Do Not install the product on top
of or nearby a heat source or dusty areas or wherever there could be corrosive environments.
Excessive operating temperature may lead to malfunction and subsequently influence the overall performance
and duration of the product itself.
In presence of Humidity such as occasional drops of water caused by condensation may damage the product. In
the event of condensation, it is advisable to wait until the area is dried. If the product has been stored in a cold
environment for a long time, it is advisable to wait a couple of hours before the actual power up to the mains
electrical line.
IMPORTANT
: only authorized personnel can open the product. Do Not try to open it without proper authorization
or else the warrantee will be Void. Remember to disconnect the mains power line and internal batteries before
proceeding to the regular maintenance every time.
2.2 CONNECTING THE CONTROL PANEL TO THE MAIN POWER LINE
230VCA
It is expected that the electrical wiring edifice/building in which the Control Panel resides is adequately furnished
with a mango-thermic switch as protection for overloads / power surges on line and short circuits.
An adequate omni-polarity switch should be in the power line frame and a accessible connector space fitting of at
least 3mm. apart. It is contemplated to adopt a uni-polarity sectioner device for the conductor phaser so that one
may identify the neutral.
The connector leads for the main power frame and internal cabling must be safely fastened by proper fastening or
fixing materials.
Shut-off main power before substituting the battery or performing other “open box” interventions on the product.
Introduce the mains power line of 230Vca in the panel container through the top right-hand corner by keeping it
distant from any internal wiring, micro-chip or main board circuitry.
Feed the power to the Control Panel adopting the proper mango-thermic power switch. The main line conductor
cable must be of at least 1,5mm² thick with a power work load which can sustain 250Vca.
NOTE: the output relays must be connected only to the circuits type SELV (not harmful power tension) in ref. to
the EN 60950-1:2001 Normative.
2.3 FUSES
On the electronic circuit board there are 5 fuses inserted on as many fittings placed vertically and they have their
feature functions described: type (F= fast, T= delayed) and nominal current.
To better learn all their general characteristics and which fuse is for which function; make reference to the
technical table reported on PART 19. Please comply to what is indicated and to not change or switch the for any
given reason or else you may alter the functioning and may cause serious faults to the Control Panel.
PART 2