Commissioning
Dosimass
22
Hauser
6.3.1
Preconditions for a zero point adjustment
Note the following before you perform a zero point adjustment:
• A zero point adjustment can be performed only with fluids that contain no gas or solid contents.
• A zero point adjustment is performed with the measuring tubes completely filled and at zero flow
(v = 0 m/s (0 ft/s)). This can be achieved, for example, with shutoff valves upstream and/or
downstream of the sensor or by using existing valves and gates (
– Normal operation
valves 1 and 2 open
– Zero point adjustment
with
pump pressure
valve 1 open / valve 2 closed
– Zero point adjustment
without
pump pressure
valve 1 closed / valve 2 open
A0008558
Fig. 15:
Zero point adjustment and shutoff valves
6.3.2
Performing a zero point adjustment
1.
Operate the system until operating conditions have settled.
2.
Stop the flow (v = 0 m/s (0 ft/s)).
3.
Check the shutoff valves for leaks.
4.
Check that operating pressure is correct.
5.
Now perform the calibration via the ZERO POINT ADJUST. function (
1
2