34 Chapter 2 Mechanical Installation
Rubber string
Removing rubber string
Figure 2-38 Floating pole of high water-level switch
Removing pipe fasteners
To prevent the long copper pipes from scratching the metal plate and being damaged, the pipes are cushioned with
foam or bound up before delivery. Remove those materials before power-on commissioning.
2.8 Installation Inspection
After the mechanical installation is completed, you should check and confirm it according to Table 2-8.
Table 2-9 Installation Inspection
Items Results
Sufficient space is left around the unit for maintenance
The equipment is installed vertically and the installation fasteners have been fixed
The pipes between the indoor unit and outdoor unit have been connected, and the ball
valves of the indoor unit and outdoor unit have been opened completely
The condensate pump (if needed) has been installed
The drain pipe has been connected
The water supply pipe for the infrared humidifier has been connected
All pipe joints have been made correctly/tested
The transportation fasteners have been removed
Irrelevant things (such as transportation material, structure material and tools) inside or
around the equipment have been cleared after the equipment is installed
The air distribution system is installed as per room design (for example, raised
floor/grilles, ductwork, etc)
After confirming the preceding points, you can start the electrical installation.