Installing Options and Accessories
5-8
Power Xpert
TM
9395 UPS (450–825 kVA) Installation and Operation Manual
164201725—Rev 10
www.eaton.com/powerquality
5.4
Installing an Optional Remote Monitor Panel II
To install RMP II wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See Chapter 7, “UPS Operating
Instructions” for shutdown instructions.
2.
Perform the procedure listed in paragraph 5.1.
3.
Securely mount the RMP II at the desired location. See Figure 5-12 for mounting hole locations.
4.
Remove the ISBM cabinet top interface conduit landing plates to drill or punch conduit holes (see
Figure 4-19).
5.
Reinstall the conduit landing plate.
6.
Install conduit between the UPS and RMP II. See Figure 5-12 for RMP II knockout hole location.
Table 5-4. Pull-Chain Wiring Terminations with MOBs
From
To
Function
UPS 1 CAN Bridge Card J3–1 (Alarm)
MOB 1 Aux 1 NC
MOB Open Alarm
UPS 1 CAN Bridge Card J3–2 (Alarm Return)
MOB 1 Aux 1 Com
UPS 1 TB2–1 (Pull Chain)
MOB 1 Aux 2 NO
Pull Chain
UPS 1 TB2–2 (Pull Chain Common)
UPS 2 TB2–2 (Pull Chain Common)
Pull Chain Common
UPS 2 CAN Bridge Card J3–1 (Alarm)
MOB 2 Aux 1 NC
MOB Open Alarm
UPS 2 CAN Bridge Card J3–2 (Alarm Return)
MOB 2 Aux 1 Com
UPS 2 TB2–1 (Pull Chain)
MOB 2 Aux 2 NO
Pull Chain
UPS 2 TB2–2 (Pull Chain Common)
UPS 3 TB2–2 (Pull Chain Common)
Pull Chain Common
UPS 3 CAN Bridge Card J3–1 (Alarm)
MOB 3 Aux 1 NC
MOB Open Alarm
UPS 3 CAN Bridge Card J3–2 (Alarm Return)
MOB 3 Aux 1 Com
UPS 3 TB2–1 (Pull Chain)
MOB 3 Aux 2 NO
Pull Chain
UPS 3 TB2–2 (Pull Chain Common)
UPS 4 TB2–2 (Pull Chain Common)
Pull Chain Common
UPS 4 CAN Bridge Card J3–1 (Alarm)
MOB 4 Aux 1 NC
MOB Open Alarm
UPS 4 CAN Bridge Card J3–2 (Alarm Return)
MOB 4 Aux 1 Com
UPS 4 TB2–1 (Pull Chain)
MOB 4 Aux 2 NO
Pull Chain
MOB 1 Aux 2 Com
MOB 2 Aux 2 Com
Pull Chain MOB Common
MOB 2 Aux 2 Com
MOB 3 Aux 2 Com
MOB 3 Aux 2 Com
MOB 4 Aux 2 Com
NOTE
If mounting to a hollow wall, secure the enclosure to a wood or metal stud within
the wall. Do not use hollow wall anchors.
NOTE
When installing signal wiring for CAN card J3 terminals, conduit must be installed
between the device and the UPS cabinet.
Содержание Power Xpert 9395 UPS
Страница 2: ......
Страница 27: ...Installation ...
Страница 28: ......
Страница 123: ...Section 2 Operation ...
Страница 124: ......
Страница 249: ......
Страница 250: ... 164201725 10 164201725 10 ...