14
Unit installation
SPLIT RACK AIR CONDITIONER USER MANUAL
UM.ICUBE2.0-SRAC.SG.0822 August 2022 www.eaton.com
Figure 2.8
ote:
N
The speed of the whole docking process should be as fast as possible as fast as possible to avoid residue
from entering the system.
•
Connect the power cord of the external unit
1. Remove the handle of the external unit, remove the screws of the wire clamp, and disassemble the wire
clamp.
2. First connect the connecting line according to the line diagram, and then press it with a fixed wire clamp.
3. Tidy up the wires, put the excess wires into the outdoor unit, cover the handle, and tighten the screws.
4. Coil the excess pipeline behind the external unit, arrange the direction of the pipeline to ensure that the
connecting pipe is horizontal and vertical. Do not touch the wall or the bracket, etc.
2.6.4 Indoor unit installation
The indoor unit is installed at the bottom of the rack and is fixed to the rack with M6 bolts to prevent the air
conditioner from moving.
The installation diagram of E04SE indoor unit is as follows:
modeFix with
M6 bolts
modeFix with
M6 bolts
Upstream air supply installaon mode
Front air supply installa on mode
Figure 2.9
Figure 2.10