13.2.1 ACR/RIM Hardware Installation
Installing ACR/RIM Interface:
1. Attach the enclosure to a wall with fasteners (not-supplied)
within 5 feet (1.5 m) of the SiteSentinel® iSite™ controller.
Enclosure needs to be in a non-hazardous location.
Figure 13-2 ACR/RIM Interface Mounting
Enclosure
2. Install the following 1/2-inch or 3/4-inch steel conduits and
wires:
•
Direct Pump Control (DPC) power source conduit and pull
three 14-AWG wires from the breaker panel.
•
ACR/RIM must be powered from a dedicated single circuit
breaker. Do not use a switch neutral breaker. The neutral
must come directly from the neutral bus in the electrical
supply panel. No other neutral circuits may be connected to
this wire.
•
Pump Communication Conduit and pull two (2) wires from
pump distribution box.
3. Mount the ACR/RIM board on the left-side stand-offs in the
enclosure.
Figure 13-3 ACR/RIM Power/Pump Conduit
•
Remove connector from CN12 ACR/RIM board and attach
output wiring from the power supply to the connector
(Polarity is NOT essential).
•
Reconnect connector to CN12 on the ACR/RIM board.
4. Attach line, neutral, and ground wires from the breaker panel
to the power connection block. ().
Figure 13-4 ACR/RIM Wiring
Содержание OPW SiteSentinel iSite
Страница 15: ...Page 15 of 145 www opwglobal com Figure 2 4 Console Connectivity ...
Страница 17: ...Page 17 of 145 www opwglobal com Figure 2 6 Wiring Connections ...
Страница 22: ...Page 22 of 145 www opwglobal com Figure 2 11 Standard Twisted Pair Petro Net Installation ...
Страница 25: ...Page 25 of 145 www opwglobal com Figure 2 14 Petro Net Over Ethernet Option ...
Страница 33: ...Page 33 of 145 www opwglobal com ...
Страница 34: ...Page 34 of 145 www opwglobal com Figure 4 1 924B Probe Installation ...
Страница 61: ...Page 61 of 145 www opwglobal com Figure 5 22 In Tank Probe Setup ...
Страница 74: ...Page 74 of 145 www opwglobal com Figure 9 3 Dry Well Monitoring Single Wall Tank ...
Страница 78: ...Page 78 of 145 www opwglobal com Figure 9 7 Double Wall Tank with Well Monitoring ...
Страница 90: ...Page 90 of 145 www opwglobal com Figure 13 7 ACR RIM Jumper Board ...
Страница 142: ...Page 142 of 145 www opwglobal com Declaration of Conformity ...
Страница 143: ...Page 143 of 145 www opwglobal com ...
Страница 146: ...Page 146 of 145 www opwglobal com NOTES ...