4. Check that the chain is flexible in the joint and that the
pin does not stick out or go through the other side
.
Figure 51
Figure 51
Chain Installation at Drive Unit
1. Insert the chain
into the underside
of the drive unit
. Make sure the
chain will be moving in the correct direction, as
indicated by the arrow
located at the
side of all chain links.
Figure 52
Figure 52
Figure 53
Figure 53
2. Feed the chain along the conveyor
by pulling it through the idler unit and back to the drive
unit.
Figure 54
Figure 54
3. Join 5 meter lengths of chain when necessary.
(See
.)
Figure 55
Figure 55
4. Tension the chain and remove links if necessary, so that
the chain will exhibit some slack at the drive unit. Put in
the stainless steel pin
at the hole
provided at drive unit and join the chain.
Figure 56
Figure 56