851-899 Rev. A
27
Dorner Mfg. Corp.
FlexMove FC (105 mm) Conveyor System
Installation
7. Adjust rail height with lower screw
.
Figure 83
Figure 83
Puck/Pallet Guiding
1. Install clip assembly
into side rail
. The end clips should be no
greater than 12
"
from the end of the conveyor.
Figure 84
Figure 84
2. Fasten clip
to conveyor with nut
on stud.
3. Tighten nuts
.
Figure 85
Figure 85
4. Attach slide rail
to guiding
86, item 2)
.
Figure 86
Figure 86
NOTE
Make sure that the studs (Figure 84, item 4)
rotate inside the channel and engage with the
conveyor.
1
1
3
2
4
NOTE
Be certain that slot (Figure 85, item 2) is
close to vertical when finished tightening nut.
NOTE
If guide length is less than 250 mm (10”), pin
plastic guide to rail using slide rail screw and
cutting flush.
1
3
2
4
2
1
1
2