Note
Wait 15 seconds for the system to recognize the PSU and determine its status.
The power supply redundancy may not occur until discovery is complete. Wait
until the new PSU is discovered and enabled before you remove the other PSU.
The PSU status indicator turns green to signify that the PSU is functioning
properly.
Figure 7 Installing a PSU
1. Release latch
2. Power cable connector
3. Power supply unit
4. Power connector
5. Handle
Replacing a server
This procedure describes how to replace a faulted PowerEdge R630 server (IDPA
node), and includes instructions to perform a full rebuild of the node .
Overview
The server replacement procedure consists of the following tasks:
1. Gather and record node information.
2. Prepare the node for replacement.
3. Remove the node from the system.
4. Install the replacement node.
5. Set up the new node.
6. Install the operating system.
7. Add the new node to the system.
8. Verify the new node functions correctly.
All logical configuration tasks in this procedure require a connection from the service
computer to port 38 on the IDPA top-of-rack switch.
Dell PowerEdge R630 Server FRUs
DELL EMC CONFIDENTIAL
44
Integrated Data Protection Appliance (IDPA)
2.1
Field Replacement Guide