20
DESIGNED SECURITY INC
800-272-3555 www.dsigo.com
1402 Hawthorne Street Bastrop, Texas 78602 Fax 512 321 9181
Email: [email protected]
INS8300
WIRING
CABLE ROUTING
The
Motor 2 and Encoder 2 cables must be routed
between the “A” and “B” Sides of each
lane. (15 ft. cables included)
Optional BarrierLocking:
Additional Locking Solenoid cable is required to be pulled along with the
standard Motor 2 and Encoder 2 control cables.
If you are installing multiple lanes, you may want to use the next lane’s cable as reference
when reconnecting the cable to the connector to assure correct wire placement. Reference
wire color/pin-out information in this document.
Begin wiring from the Right-most bollard
when facing from the Entrance (un-secure) side.
This bollard should have the Electronics Package in the side facing into the lane.
Leave adequate service loop in cables. Route cables neatly in pedestal.
Check conduit or cableway for airflow
using a strip of tissue paper. If airflow is detected,
use paper or foam material to block airflow through conduit access hole.
Airflow through
chassis may result in rapid dust accumulation on sensor optics which can lead to false alarms
and frequent cleaning requirements.
Power Cable must be of sufficient Gauge
to provide 24VDC under load, measured at the
Power Input Connector.
(See Power Wire Gauge Calculator in Appendix)
CABLE TERMINATION
Use the included WAGO™ tool to
remove and connect the wires on
each of the WAGO™ connectors
.
Photo shows
WAGO™ tool in use.
Hook over edge and press tab into
connector to release spring holding
each wire.
Содержание DSI ES8300
Страница 1: ...ES8300 ACRYLIC BARRIER OPTICAL TURNSTILE INSTALLATION AND OPERATION INSTRUCTIONS...
Страница 2: ......
Страница 4: ......
Страница 6: ......
Страница 8: ......
Страница 10: ......
Страница 19: ...WIRING...
Страница 24: ......
Страница 25: ...SETUP OPERATION...
Страница 26: ......
Страница 32: ......