Chapter 13
GB
DIAGRAMS AND ATTACHMENTS
Aerial work platform
B-LIFT 18 HV
5
COD. UM0287_GB | REV. 00 | ED: 09/18
13.3
Maintenance checklist
Some tables have been included below as a reference in order to make it easier to record maintenance
work (see section 8.3).
BEFORE EACH USE
Description of operation
Check
Section
Performed
R
Not performed
T
Visual inspection
£
£
6.3.1
Check use and maintenance manual
£
£
6.3.1
Check legibility of plates and labels
£
£
6.3.1
Check for any damage, for missing, loose or
detached parts.
£
£
6.3.1
Check welds, pins and joints
£
£
6.3.1
Check for any oil leaks
£
£
8.6
Check pressures
£
£
8.6.3
Hydraulic oil level check
£
£
8.6.5
Check hydraulic oil ilter clogging indicators
£
£
8.6.6
Check the operation of the controls in the platform
and on the ground
£
£
8.7.1
Check safety devices (Emergency Stop)
£
£
8.7.1
Test limit switches
£
£
8.7.2
Test power supply differential circuit breaker in the
platform.
£
£
15.3
Description of operation
Check
Section
Performed
R
Not performed
T
Visual inspection
£
£
6.3.1
Check use and maintenance manual
£
£
6.3.1
Check legibility of plates and labels
£
£
6.3.1
Check for any damage, for missing, loose or
detached parts.
£
£
6.3.1
Check welds, pins and joints
£
£
6.3.1
Check for any oil leaks
£
£
8.6
Check pressures
£
£
8.6.3
Hydraulic oil level check
£
£
8.6.5
Check hydraulic oil ilter clogging indicators
£
£
8.6.6
Check the operation of the controls in the platform
and on the ground
£
£
8.7.1
Check safety devices (Emergency Stop)
£
£
8.7.1
Test limit switches
£
£
8.7.2
Test power supply differential circuit breaker in the
platform.
£
£
15.3